Practical guide

Construction valuation template UK 2026

Copy a 2026 construction valuation template with cumulative work, current period, variations, materials on site, retention and prior certifications.

Published 8 September 2026

A construction valuation records the value of work completed to date, approved variations, materials on site, retention and previous amounts. It supports an application for payment; it is not automatically the tax invoice.

Use this 2026 template for a subcontract package.

Construction valuation template

Subcontractor: [Legal name]
Contractor: [Legal name]
Project/site: [ ]
Subcontract/PO: [ ]
Valuation number: [ ]
Valuation date: [Date in 2026]
Period ending: [ ]

Valuation summary This period Cumulative
Original subcontract work £[ ] £[ ]
Approved variations £[ ] £[ ]
Materials on site, if allowed £[ ] £[ ]
Gross value £[ ] £[ ]
Retention -£[ ] -£[ ]
Previously certified/applied -£[ ]
Current amount £[ ] £[ ]

Supporting documents: [measurements, programme, photos, signed sheets, delivery notes, variation approvals]

Worked valuation example

Item Cumulative value
Original work completed £42,000
Approved variations £3,500
Gross valuation £45,500
Retention at 5% -£2,275
Net cumulative value £43,225
Previously certified -£31,000
Current application £12,225

This is an illustrative 2026 example. Use the percentage and valuation method in the actual subcontract.

Separate this period from cumulative value

Cumulative figures show the full job position. The current amount removes what was already certified or invoiced.

Do not invoice the cumulative total again. Tie the current invoice to the certified or agreed amount for this period.

Measure the work package

Use the same work breakdown as the subcontract:

  • preliminaries
  • measured work sections
  • milestones
  • agreed daywork
  • approved variations
  • materials on site
  • retention

This lets the contractor compare the valuation with the original price and prior month.

Variations

Only include variations at the status allowed by the contract. Separate:

  • instructed and priced
  • instructed but not agreed
  • submitted for approval
  • rejected or withdrawn

Do not hide an unagreed variation inside the original work line. Use a reference, date and supporting instruction.

Materials on site

Some contracts allow properly stored and evidenced materials to be valued before installation. Others do not.

If included, record:

  • description and quantity
  • delivery location
  • ownership and insurance position
  • delivery note or supplier invoice
  • amount previously valued

Follow the subcontract rather than a generic template.

Retention

Show the current retention deduction and cumulative amount held. The rate, cap and release events come from the contract.

The retention invoice guide explains release and final-account records.

From valuation to invoice

The contractor may certify a different amount from the application. Raise the invoice according to the contractual process and show:

  • invoice number and date
  • supply period
  • certified or agreed current value
  • VAT treatment
  • CIS labour and materials split
  • retention where applicable
  • amount due

The subcontractor invoice template gives the invoice layout.

VAT and CIS

A valuation records value. VAT and CIS are applied when the payment document is prepared under the correct rules.

Keep the figures separate:

  • net taxable supply
  • reverse-charge VAT or normal VAT
  • CIS deduction base
  • CIS deduction
  • cash due

Valuation checklist for 2026

  • Does the work breakdown match the subcontract?
  • Are this-period and cumulative figures separate?
  • Have previous certifications been deducted?
  • Are variations individually referenced?
  • Are materials on site allowed and evidenced?
  • Is retention calculated under the contract?
  • Are supporting measurements attached?
  • Does the resulting invoice use the correct tax treatment?

Sendinvo handles the invoice after the valuation: customer, lines, CIS deduction, reverse-charge wording and payment due. Start free when the current amount has been agreed.